A simple CPM network has three activities,D,E,and F.D is an immediate predecessor of E and of F.E is an immediate predecessor of F.The activity durations are D=4,E=3,F=8.
A) The critical path is D-E-F,duration 15.
B) The critical path is D-F,duration 12.
C) Slack at D is 3 periods.
D) Slack at E is 3 periods.
E) Both A and C are true.
Correct Answer:
Verified
Q45: Slack is the amount of time an
Q48: Identify, in order, the six steps basic
Q50: The _ is the computed longest time
Q51: Which of the following statements regarding critical
Q53: Activity D on a CPM network has
Q54: Which of the following statements regarding CPM
Q55: The critical path for the network activities
Q57: The difference between AON and AOA networks
Q58: What is the basic difference between PERT
Q61: Explain why the critical path is the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents