Keith assembles peanut valves and the recorded data is displayed in the table.During one of the cycles,he pauses to answer a phone call from his friend who suggests that he seek employment elsewhere.Keith fields calls with some regularity,but that's not considered part of his routine job responsibilities.What is the select time for this job element if Keith is rated at 75%?
A) Greater than or equal to 3.2 minutes
B) Less than 3.2 minutes but greater than or equal to 2.8 minutes
C) Less than 2.8 minutes but greater than or equal to 2.4 minutes
D) Less than 2.4 minutes
Correct Answer:
Verified
Q15: Timing the work elements using the snap-back
Q28: Traditional work measurement techniques often are viewed
Q29: Garman observes a worker assembling peanut
Q30: Garman observes a worker assembling peanut
Q31: A manager is interested in setting a
Q34: When using a time-study approach,the standard time
Q36: A time-study analyst is attempting to determine
Q37: Which one of the following statements about
Q38: An analyst using a time study approach:
A)
Q38: Keith assembles peanut valves and the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents