Table 3.4 Activity A B C D E F G H I J K L M N Immediate Predecessor(s) ⋯⋯⋯ A B B C E F D I K,H G L, J Time (weeks) 22222222222222 -Using Table 3.4,what is the latest finish time for activity D?
A) 4 weeks B) 6 weeks C) 8 weeks D) 10 weeks