Table 39
All Activity Times for the Project Are in Weeks

Question 97

Multiple Choice

Table 3.9
All activity times for the project are in weeks.
 Activity  Optimistic  Time  Most Likely  Time  Pessimistic  Time  Immediate  Predecessor(s)   A 345 B 579 C 2310 A  D 258 B  E 177 B  F 357 C,D  G 789 D,E  H 2610F\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Optimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Most Likely } \\\text { Time }\end{array} & \begin{array} { c } \text { Pessimistic } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} \\\hline \text { A } & 3 & 4 & 5 & \cdots \\\text { B } & 5 & 7 & 9 & - \\\text { C } & 2 & 3 & 10 & \text { A } \\\text { D } & 2 & 5 & 8 & \text { B } \\\text { E } & 1 & 7 & 7 & \text { B } \\\text { F } & 3 & 5 & 7 & \text { C,D } \\\text { G } & 7 & 8 & 9 & \text { D,E } \\\text { H } & 2 & 6 & 10 & F \\\hline\end{array}
-Using Table 3.9,what is the critical path of this project?


A) A-C-F-H
B) B-D-F-H
C) B-D-G
D) B-E-G

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents