Multiple Choice
Table 3.9
All activity times for the project are in weeks.
-Using Table 3.9,what is the probability that the project will be completed in 24 weeks or less? You will need to refer to a standard normal table to answer the question.
A) less than or equal to 55%
B) greater than 55% but less than or equal to 65%
C) greater than 65% but less than or equal to 75%
D) greater than 75%
Correct Answer:
Verified