Table 3.7 Activity ABCDEFGHIJKL Immediate Predecessor (s) ⋯−A⋯AA,BA,B,CD,EEE,FG,H,IH,II Time (weeks) 34242162436 -Using Table 3.7,what is the critical path for this project?
A) B-E-H-K B) B-E-H-J C) A-E-G-J D) C-F-I-L
Correct Answer: