Multiple Choice
If a project has multiple critical paths,which of the following variances should be used in analyzing project completion time probabilities?
A) the critical path with the smallest variance
B) the critical path with the largest variance
C) the sum of the variances for all critical paths
D) the average variance of the critical paths
Correct Answer:
Verified