Multiple Choice
Table 3.1
Time (weeks)
-Using Table 3.1,if the expected times for activities A,G,and H increased by 2,3,and 4 weeks,respectively,by how many weeks would the project's earliest expected time of completion increase?
A) less than or equal to 2 weeks
B) greater than 2 weeks but less than or equal to 4 weeks
C) greater than 4 weeks but less than or equal to 6 weeks
D) greater than 6 weeks
Correct Answer:
Verified