Solved

Table 31
Time (Weeks) -Using Table 3

Question 69

Multiple Choice

Table 3.1
Time (weeks)
 Activity  Immediate  Predecessor(s)   Most  Optimistic  Most  Likely  Most  Pessimistic  A 1123 B  A 2412 C  A 123 D  B 678 E  B,C 101214 F  D 234 G  E,F 1515 H  A 2514\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Most } \\\text { Optimistic }\end{array} & \begin{array} { c } \text { Most } \\\text { Likely }\end{array} & \begin{array} { c } \text { Most } \\\text { Pessimistic }\end{array} \\\hline \text { A } & - 1 & 1 & 2 & 3 \\\text { B } & \text { A } & 2 & 4 & 12 \\\text { C } & \text { A } & 1 & 2 & 3 \\\text { D } & \text { B } & 6 & 7 & 8 \\\text { E } & \text { B,C } & 10 & 12 & 14 \\\text { F } & \text { D } & 2 & 3 & 4 \\& & & & \\\text { G } & \text { E,F } & 1 & 5 & 15 \\\text { H } & \text { A } & 2 & 5 & 14 \\\hline\end{array}
-Using Table 3.1,what is the earliest expected time of completion of the whole project?


A) less than or equal to 19 weeks
B) greater than 19 but less than or equal to 21 weeks
C) greater than 21 but less than or equal to 24 weeks
D) greater than 24 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents