Table 3.2
Time (days)
-Using Table 3.2,if the project manager wants at least a 98% probability that the project will be completed on or before the due date,what is the shortest project due date that will satisfy the manager? You will need to refer to a standard normal table to answer the question.
A) less than or equal to 28 days
B) greater than 28 days but less than or equal to 30 days
C) greater than 30 days but less than or equal to 32 days
D) greater than 32 days
Correct Answer:
Verified
Q21: Which one of the following best describes
Q21: Assume that activity G has the following
Q25: Figure 7.2 Q35: Activity slack is defined as: Q62: Table 3.2 Q64: When using the beta probability distribution to Q65: Table 3.2 Q68: Table 3.3 Q69: Table 3.1 Q71: Table 3.3 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents
A) latest start
Time (days)
Time (days)
Time (weeks)