Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
-Use the information in Table 13.3.Which one of the following statements on item C is TRUE?
A) There will be no action notices for item C.
B) There will be exactly one action notice, to release a new order.
C) There will be exactly two action notices, to release a new order and delay the scheduled receipt.
D) There will be more than two action notices.
Correct Answer:
Verified
Q15: Table 13.7. Q18: Table 13.7 Q27: Table 13.7 Q38: Table 13.7. Q44: Table 13.4 Q102: Table 13.6 Q103: Table 13.5 Q104: Table 13.3 Q105: Table 13.7 Q112: Table 13.5 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents