Table 13.4
Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS
start quantities.
Week
Bill of Material
-Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B.
-Subassembly B uses 1 each of component D.
Selected Inventory Data
Item
-Use the information in Table 13.4. What are the total planned receipts for item D? (Sum up the planned receipts for all periods.)
A) less than or equal to 80 units
B) greater than 80 units but less than or equal to 100 units
C) greater than 100 units but less than or equal to 240 units
D) greater than 240 units.
Correct Answer:
Verified
Q39: One of the three types of MRP
Q40: MRP explosion means estimating the total number
Q41: Table 13.6. Q42: Management wishes to use a FOQ lot- Q43: Which of the following statements on MRP Q45: Table 13.4 Q46: Which of the following statements about lot-
Consider the MPS, BOM and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents