One of the Three Types of MRP Action Notices Possible

Question 39

Multiple Choice

One of the three types of MRP action notices possible is releasing a new order. Which one of the following statements is TRUE about releasing a new order?


A) Release an order when the first period's gross requirements quantity is equal to zero.
B) Release a separate order for service parts.
C) Release an order when there is a nonzero quantity in the scheduled receipt row.
D) Release an order when there is a nonzero quantity in the first period's planned order release row.