Table 134
Consider the MPS, BOM and Inventory Data Shown Below

Question 45

Multiple Choice

Table 13.4
Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities.
Week
 Week 123456 MPS 8080\begin{array} { | c | c | c | c | c | c | c | } \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\\hline \text { MPS } & & & 80 & 80 & & \\\hline\end{array}
Bill of Material
-Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B.
-Subassembly B uses 1 each of component D.
Selected Inventory Data Item
 Table 13.4 Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities. Week  \begin{array} { | c | c | c | c | c | c | c | }  \hline \text { Week } & 1 & 2 & 3 & 4 & 5 & 6 \\ \hline \text { MPS } & & & 80 & 80 & & \\ \hline \end{array}  Bill of Material -Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B. -Subassembly B uses 1 each of component D. Selected Inventory Data Item    -Use the information in Table 13.4. When does the first planned order release for item C occur? A)  Week 1 or 2 B)  Week 3 C)  Week 4 D)  No planned order releases needed

-Use the information in Table 13.4. When does the first planned order release for item C occur?


A) Week 1 or 2
B) Week 3
C) Week 4
D) No planned order releases needed

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents