Table 13.4
Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS start quantities.
Week
Bill of Material
-Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B.
-Subassembly B uses 1 each of component D.
Selected Inventory Data Item
-Use the information in Table 13.4. When does the first planned order release for item C occur?
A) Week 1 or 2
B) Week 3
C) Week 4
D) No planned order releases needed
Correct Answer:
Verified
Q40: MRP explosion means estimating the total number