Table 13.8
Sunshine Manufacture produces three products, X, Y, and Z. The production of these end items is controlled by an MRP system. Each end item X is assembled with two components of A and one component of B. Each end item of Y is assembled with two components of C and one component of A, each component of C is manufactured from one unit of B. End item Z is assembled from one unit of D and one unit of C, D is manufactured from one unit of A, and C is manufactured from one unit of B.
-Use the information in Table 13.8.If item C has a manufacturing lead time of two weeks and a planned receipt of 65 units is needed in week 4,which of the following statements is TRUE?
A) The planned order release in week 2 for item C is 130 units.
B) The gross requirements for item B in week 4 are at least 65 units.
C) The gross requirements for item B in week 2 is 130 units.
D) The gross requirements for item B in week 2 is 65 units.
Correct Answer:
Verified
Q64: A(n) _ is a record of
Q65: MRP _ is a process that converts
Q67: _ demand occurs because the quantity
Q79: A(n) _ is an intermediate item that
Q80: _ is the degree to which a
Q90: _ allow an organization to view
Q91: In an MRP system, from what sources
Q93: _ are orders that have been placed
Q97: _ ties the basic MRP system to
Q161: Discussed why lots sizing is important in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents