In a typical building project, the coordination of the building's design is done by the
A) general contractor.
B) owner.
C) architect.
D) building official of the city.
E) any one of the above, depending on the type of building.
Correct Answer:
Verified
Q3: The program for a building project is
Q4: The construction document set consists of
A)construction drawings,
Q5: In MasterFormat, Division 02 refers to
A)Procurement and
Q6: The construction drawings of a building project
Q7: The term MEP is an acronym for
A)mechanical,
Q9: In MasterFormat, Division 04 refers to
A)General Requirements.
B)Metals.
C)Existing
Q10: The bidding documents include
A)construction drawings, specifications, addenda,
Q11: Who is responsible for ensuring the safety
Q12: The delivery of a typical building project,
Q13: MasterFormat consists of
A)20 divisions.
B)30 divisions.
C)40 divisions.
D)50 divisions.
E)none
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents