The final completion inspection of the project is conducted by the
A) building official of the city.
B) owner with the help of the architect.
C) architect.
D) architect and the building official of the city.
E) architect with the help of consultants.
Correct Answer:
Verified
Q21: The shop drawings are prepared by the
A)structural
Q22: When does the owner receive manufacturers' warranties
Q23: A record document set includes
A)as- built construction
Q24: The certificate of substantial completion is issued
Q25: In which of the following project delivery
Q27: The project manual includes the project's construction
Q28: The owner is required to provide payment
Q29: A contract document set consists of
A)construction drawings,
Q30: The primary purpose of the contract modification
Q31: Of the various project delivery methods described
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents