In setting up a kanban control system you need to determine the number of kanban card sets needed. If the expected demand during lead time is 50 per hour, the safety stock is 20% of the demand during lead time, the container size is 4. If the lead time to replenish an order is 8 hours, what number of kanban card sets is needed?
A) 60
B) 80
C) 90
D) 120
E) 150
Correct Answer:
Verified
Q51: Which of the following are related to
Q55: You have been called in as a
Q56: Applying lean concepts in manufacturing balances increases
Q58: In setting up a kanban control system
Q64: An activity where the parts that go
Q65: To develop a lean manufacturing system a
Q66: Which of the following is a lean
Q67: Which of the following statements holds true
Q75: Group technology (GT) is credited with which
Q83: Which of the following is not listed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents