A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the probability that the project is completed in 31 days? 
A) 0.055
B) 0.092
C) 0.125
D) 0.187
Correct Answer:
Verified
Q80: Use the information in the table to
Q83: A project has the precedence requirements and
Q85: One approach to reducing project length would
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents