A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the probability that the project takes more than 34 days? 
A) 0.788
B) 0.212
C) 0.945
D) 0.055
Correct Answer:
Verified
Q84: Activity float is the difference between the
Q85: One approach to reducing project length would
Q85: A gentleman farmer maniacally works on academic
Q86: The PERT technique assumes that durations are
Q87: Use the values in the table to