A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity. Which is a legitimate hammock activity for this project? 
A) Combine activities A, B, C
B) Combine activities B, E, H
C) Combine activities E, F
D) Combine activities G, H, I
Correct Answer:
Verified
Q84: Activity float is the difference between the
Q85: One approach to reducing project length would
Q86: The PERT technique assumes that durations are
Q87: Use the values in the table to