Table
A company uses a kanban system. The daily demand for part A is 4000 units. The average waiting time for a container of parts is day. The processing time for a container of part is day, and a container holds 300 units.
-Use the information in Table 8.3. How many kanban containers would be required if a 15 % efficiency factor is used?
A) 10 or less
B) 11 or 12
C) 13 or 14
D) 15 or more
Correct Answer:
Verified
Q27: All of the following wastes but one
Q28: The final assembly schedule in a JIT
Q29: Implementing a JIT system
A) requires an examination
Q30: Table
Q31: Table
Q33: In a JIT II system the
A) sales
Q34: In JIT systems, if a defective product
Q35: Suppliers often cite which of the following
Q36: According to JIT, an approach to reduce
Q37: Which of the following are not a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents