The single milling machine at Stout Manufacturing was severely overloaded last year. The plant operates eight hours per day, five days per week, and 50 weeks per year. Management prefers a capacity cushion of 15 percent. Two major types of products are routed through the milling machine. The annual demand for product A is 3000 units and 2000 units for product B. The batch size for A is 20 units and 40 units for B. The standard processing time for A is 0.5 hours/unit and 0.8 for B. The standard setup time for product A is 2 hours and 8 hours for product B. How many new milling machines are required if Stout does not resort to any short- term capacity options?
A) no new machines
B) 1 or 2 new machines
C) 3 or 4 new machines
D) more than 4 new machines
Correct Answer:
Verified
Q3: A wait- and- see strategy in regard
Q4: Table 5.2
High Tech, Inc. is producing two
Q5: What information would managers use to choose
Q6: Table 5.2
High Tech, Inc. is producing two
Q7: Which of the following is NOT a
Q9: Which one of the following is NOT
Q10: Table 5.2
High Tech, Inc. is producing two
Q11: Up, Up & Away is a producer
Q12: Which one of the following statements about
Q13: Innovative Inc. is experiencing a boom
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents