Table 5.2
High Tech, Inc. is producing two types of products: A and B. Both are produced at the same sawing operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic) . The demand forecasts, batch sizes (units/batch) , processing times (hr/unit) , and setup times (hr/batch) follow.
The sawing machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 10 percent capacity cushion.
-Using the information from Table 5.2, what is the maximum number of machines needed (assuming no reliance on short- term option) ?
A) less than or equal to 25
B) more than 25 but less than or equal to 28
C) more than 28 but less than or equal to 31
D) more than 31
Correct Answer:
Verified
Q1: The Northern Manufacturing Company is producing
Q2: Table
Q3: A wait- and- see strategy in regard
Q4: Table 5.2
High Tech, Inc. is producing two
Q5: What information would managers use to choose
Q7: Which of the following is NOT a
Q8: The single milling machine at Stout Manufacturing
Q9: Which one of the following is NOT
Q10: Table 5.2
High Tech, Inc. is producing two
Q11: Up, Up & Away is a producer
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents