Table 13.3
Consider the following MPS, BOM, and inventory data. You will need a blank MRP record to answer the question(s) .
Week
Bill of Material
-End item A uses 1 each of component C and 1 each of subassembly D.
-Subassembly D uses 2 each of component E and 2 each of component F.
-End item B uses 1 each of component C and 2 each of component F.
Selected Inventory Data
Item
Master Production Schedule: the following table shows the MPS start quantities.
-Use the information in Table 13.3. Which one of the following statements about item E is TRUE?
A) There will be an action notice to expedite the scheduled receipt up to week 2.
B) There is one planned receipt for the next 6 weeks.
C) There is a planned order release of 250 units in week 3.
D) There is a planned receipt of 250 units in week 2.
Correct Answer:
Verified
Q2: One of the differences between Enterprise Resource
Q3: The action notice is a
A) secret document
Q4: Table 13.6 Q5: Complete the following MRP record in Q6: Management wishes to use a POQ lot- Q7: Which best defines the gross requirements for Q8: Which of the following statements about MRP Q9: Use the following MRP record to answer Q10: Use the following MRP record to answer Q11: The purpose of Finite Capacity Scheduling is![]()
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents