Consider the Following Activity Schedule Chart for a Maintenance Project

Question 53

Essay

Consider the following activity schedule chart for a maintenance project.  Activity  ES  EF  IS  LF  A 0617 B 0505 C 614715 D 6101418 E 14161517 F 514514 G 14171417 H 14191621 I 10131821 J 17211721\begin{array}{ccccr}\text { Activity } & \text { ES } & \text { EF } & \text { IS } & \text { LF } \\\text { A } & 0 & 6 & 1 & 7 \\\text { B } & 0 & 5 & 0 & 5 \\\text { C } & 6 & 14 & 7 & 15 \\\text { D } & 6 & 10 & 14 & 18 \\\text { E } & 14 & 16 & 15 & 17 \\\text { F } & 5 & 14 & 5 & 14 \\\text { G } & 14 & 17 & 14 & 17 \\\text { H } & 14 & 19 & 16 & 21 \\\text { I } & 10 & 13 & 18 & 21 \\\text { J } & 17 & 21 & 17 & 21\end{array} A.What are the slack values?
B.Identify the activities on the critical path.
C.If the time is in weeks, what is the impact of a two week delay in activity D, H, or C?

Correct Answer:

verifed

Verified

A.
(A = 1; B = 0; C = 1; D = 8; E = 1; F...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents