Solved

In a PERT Network, You Are Given the Following Data

Question 48

Essay

In a PERT network, you are given the following data with times in weeks.  Activity  Immediate  Optimistic  Most Likely  Pessimistic  Predecessors  Time  Time  Time  A  G 1113 B 4920 C  A 21114 D  A, B 5613 E  D 3611 F  C, D 91011 G  E , F 72021\begin{array}{ccccc}\text { Activity } & \text { Immediate } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\& \text { Predecessors } & \text { Time } & \text { Time } & \text { Time }\\\text { A } & -- & \text { G } & 11 & 13 \\\text { B } & -- & 4 & 9 & 20 \\\text { C } & \text { A } & 2 & 11 & 14 \\\text { D } & \text { A, B } & 5 & 6 & 13 \\\text { E } & \text { D } & 3 & 6 & 11 \\\text { F } & \text { C, D } & 9 & 10 & 11 \\\text { G } & \text { E }, \text { F } & 7 & 20 & 21\end{array}
A.What is the critical path?
B.What is the probability the project will be completed within one year (52 weeks)?

C.Which activity has the most slack?

Correct Answer:

verifed

Verified

A.
(A - C - F - G)

...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents