Brisebois Engineering Ltd Actual Results Required:
A) Calculate the Revenue, Expense, and Profit for Each

Question 91

Essay

Brisebois Engineering Ltd.signed a contract to build a bridge and traffic interchange for three
small municipalities.Construction will occur over a four-year period.The following data pertain to the contract and subsequent construction:  Contract price: $1,750,000 Estimated costs: 1,250,000 (remained unchanged throughout contract period) \begin{array}{lll}\text { Contract price: } & \$ 1,750,000 \\\text { Estimated costs: } & 1,250,000 \text { (remained unchanged throughout contract period) }\end{array} Actual Results:  Year  Costs  Receipts 1$650,000$205,0002$325,000$137,0003$200,000$600,0004$75,000$408,000\begin{array}{lll}\text { Year } & \text { Costs } & \text { Receipts }\\1 & \$ 650,000 & \$ 205,000 \\2 & \$ 325,000 & \$ 137,000 \\3 & \$ 200,000 & \$ 600,000 \\4 & \$ 75,000 & \$ 408,000\end{array} Required:
A) Calculate the revenue, expense, and profit for each of the four years using the:
i.Cost recovery method
ii.Percentage of completion
B) Calculate the gross profit margin for each year under each alternative

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents