Kwen Enterprises, a Public Company, Has Been Hired by the New

Question 92

Essay

Kwen Enterprises, a public company, has been hired by the new government of North Mokar to build a small airport with two runways for commercial use.North Mokar is a small country in Africa that has just elected its first democratic government.Kwen has agreed to the project, although they fear that if rebels overtake the new government, the airport will be used for military purposes and any outstanding amounts owing might not be paid.Kwen planned to complete the project as quickly as possible and has prepared the estimates below.They have a lot of experience in building similar projects elsewhere, so they are confident with their cost estimates and their ability to complete the project on time.  Costs  Billings to government 1st  year $1,750,000$2,000,0002nd  yea $1,550,000$1,700,000\begin{array}{lll}&\text { Costs } & \text { Billings to government } \\1^{\text {st }} \text { year } & \$ 1,750,000 & \$ 2,000,000 \\2^{\text {nd }} \text { yea } & \$ 1,550,000 & \$ 1,700,000\end{array} Required:
A) Compute the revenue and expenses for each year using the percentage-of-completion method.B) Compute the revenue and expenses for each year using the cost recovery method.
C) What facts would make you recommend the use of the percentage-of-completion method for this project? D) What facts would make you recommend the use of the cost recovery method for this project?
E) Which method should Kwen use?

Correct Answer:

verifed

Verified

A) blured image B) blured image C) Kwen has a lot of experience ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents