Use the following information for questions.
Eilert Construction Company had a contract starting April 2011, to construct a $15,000,000 building that is expected to be completed in September 2012, at an estimated cost of $13,750,000.At the end of 2011, the costs to date were $6,325,000 and the estimated total costs to complete had not changed.The progress billings during 2011 were $3,000,000 and the cash collected during 2011 was $2,000,000.Eilert uses the percentage-of-completion method.
-At December 31, 2011, Eilert would report Construction in Process in the amount of
A) $6,900,000.
B) $6,325,000.
C) $5,900,000.
D) $575,000.
Correct Answer:
Verified
Q60: Use the following information for questions.
In 2012,
Q61: The following information relates to questions
Q62: Wynn, Inc.has a contract to construct a
Q63: Use the following information for questions.
Gorman Construction
Q64: Use the following information for questions.
Kiner, Inc.began
Q66: Lark Corp.has a contract to construct a
Q67: The following information relates to questions
Q68: Lark Corp.has a contract to construct a
Q69: Remington Construction Company uses the percentage-of-completion method.During
Q70: Use the following information for questions.
Gomez, Inc.began
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents