Use the following information for questions.
In 2012, Fargo Corporation began construction work under a three-year contract.The contract price is $2,400,000.Fargo uses the percentage-of-completion method for financial accounting purposes.The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract.The financial statement presentations relating to this contract at December 31, 2012, follow:

-How much cash was collected in 2012 on this contract?
A) $100,000
B) $140,000
C) $20,000
D) $240,000
Correct Answer:
Verified
Q55: Some of the initial franchise fee may
Q56: The following information relates to questions
Cooper
Q57: Use the following information for questions.The contract
Q58: Use the following information for questions.The contract
Q59: Cost estimates on a long-term contract may
Q61: The following information relates to questions
Q62: Wynn, Inc.has a contract to construct a
Q63: Use the following information for questions.
Gorman Construction
Q64: Use the following information for questions.
Kiner, Inc.began
Q65: Use the following information for questions.
Eilert Construction
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents