The following information relates to questions
Cooper Construction Company had a contract starting April 2012, to construct a $9,000,000 building that is expected to be completed in September 2014, at an estimated cost of $8,250,000.At the end of 2012, the costs to date were $3,795,000 and the estimated total costs to complete had not changed.The progress billings during 2012 were $1,800,000 and the cash collected during 2012 was 1,200,000.
-At December 31, 2012 Cooper would report Construction in Process in the amount of:
A) $345,000
B) $3,795,000
C) $4,140,000
D) $3,540,000
Correct Answer:
Verified
Q51: On January 1, 2012, Hood Company sold
Q53: Hayes Construction Corporation contracted to construct a
Q55: Some of the initial franchise fee may
Q55: Types of franchising arrangements include all of
Q57: Use the following information for questions.The contract
Q58: Use the following information for questions.The contract
Q59: Cost estimates on a long-term contract may
Q60: Use the following information for questions.
In 2012,
Q61: The following information relates to questions
Q66: Occasionally a franchise agreement grants the franchisee
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents