Use the following information for questions.The contract calls for progress billings and payments of $620,000 each quarter.The total contract price is $7,440,000 and Seasons estimates total costs of $7,100,000.Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2010.
-At December 31, 2011, Seasons Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $7,200,000 due to unanticipated price increases.What is the total amount of Construction Expenses that Seasons will recognize for the year ended December 31, 2011?
A) $5,400,000
B) $3,150,000
C) $3,195,000
D) $3,270,000
Correct Answer:
Verified
Q53: Hayes Construction Corporation contracted to construct a
Q55: Some of the initial franchise fee may
Q55: Types of franchising arrangements include all of
Q56: The following information relates to questions
Cooper
Q58: Use the following information for questions.The contract
Q59: Cost estimates on a long-term contract may
Q60: Use the following information for questions.
In 2012,
Q61: The following information relates to questions
Q62: Wynn, Inc.has a contract to construct a
Q66: Occasionally a franchise agreement grants the franchisee
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents