Use the following information for questions.The contract calls for progress billings and payments of $620,000 each quarter.The total contract price is $7,440,000 and Seasons estimates total costs of $7,100,000.Seasons estimates that the building will take 3 years to complete, and commences construction on January 2, 2010.
-At December 31, 2010, Seasons estimates that it is 30% complete with the construction, based on costs incurred.What is the total amount of Revenue from Long-Term Contracts recognized for 2010 and what is the balance in the Accounts Receivable account assuming Cannon Cafe has not yet made its last quarterly payment?
Correct Answer:
Verified
Q53: Hayes Construction Corporation contracted to construct a
Q55: Some of the initial franchise fee may
Q56: The following information relates to questions
Cooper
Q57: Use the following information for questions.The contract
Q59: Cost estimates on a long-term contract may
Q60: Use the following information for questions.
In 2012,
Q61: The following information relates to questions
Q62: Wynn, Inc.has a contract to construct a
Q63: Use the following information for questions.
Gorman Construction
Q66: Occasionally a franchise agreement grants the franchisee
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents