A team planning for the market launch of a new video game has employed FMEA to assess the relative importance of possible risks. One risk they identified, failure of the logistics system to deliver games to key retailers by the promised date, produced the following scores based on team input:
The RPN for this risk would be:
A) 45
B) 15
C) 9
D) 450
E) 44
Correct Answer:
Verified
Q4: When is the best time for project
Q5: Which of the following is NOT a
Q6: Which of the following does a team
Q7: RPNs Risk Priority Numbers) are used to
Q8: Which of the following is a category
Q9: A fishbone diagram, also known as an
Q11: Which of the following uncertainty assessment tools
Q12: During the dot-voting process for the Gut
Q13: The government of an unnamed country has
Q14: Members of a project team have used
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents