Members of a project team have used FMEA to calculate the RPN for one of the risks it has identified. The RPN is 200. Which of the following combinations could have produced this score?
A) Severity: 50, Likelihood: 100, Detection Difficulty: 50
B) Severity: 100, Likelihood: 2, Detection Difficulty: 1
C) Severity: 50, Likelihood: 2, Detection Difficulty: 10
D) Severity: 199, Likelihood: 1, Detection Difficulty: 0
E) Severity: 5, Likelihood: 5, Detection Difficulty: 8
F) B and E both are possible
G) A and D are both possible
Correct Answer:
Verified
Q4: When is the best time for project
Q5: Which of the following is NOT a
Q6: Which of the following does a team
Q7: RPNs Risk Priority Numbers) are used to
Q8: Which of the following is a category
Q9: A fishbone diagram, also known as an
Q10: A team planning for the market
Q11: Which of the following uncertainty assessment tools
Q12: During the dot-voting process for the Gut
Q13: The government of an unnamed country has
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents