Question 1
Multiple Choice
Given the following information about a project: EV = $1,000,000 PV = $2,000,000 AC = $3,000,000 BAC = $4,000,000 What can we legitimately say about this project if this is the only information we have?
Question 2
Multiple Choice
Given the following information about a project portfolio, what would be the most likely outcome associated with taking 10% of the resources from project A and giving them to project B? Assume the axis of the graph is the point where both CPI and SPI are equal to 1.
Question 3
Multiple Choice
Given the following information about a project: EV = $20,000 PV = $15,000 AC = $25,000 BAC = $40,000 Estimated Duration = 6 months Assuming this is the only information available, which of these can we legitimately conclude about the project?
Question 4
Multiple Choice
Given the following information at week 12 of a 54-week project: PV = 1,200 hours EV = 1,400 hours AC = 1,000 hours Schedule variance percent SV%) and cost variance percent CV%) , respectively, would be: