A project team has worked for six months on a solar power project that will involve an entirely new technology. Early in the project, they chose a very specific approach from among several available, and they have continued pursuing this approach in spite of repeated failures. The project sponsor has warned them the project will be cancelled if they do not achieve success within one month. The team decides to stick with the current approach and work harder rather than experimenting with an alternative technology option. Which phenomenon best describes what has influenced the team's decision?
A) Murphy's Law
B) Parkinson's Law
C) Student Syndrome
D) Scope Creep
E) Escalation of Commitment
F) Pareto's Law
Correct Answer:
Verified
Q5: Given the following information at week 19
Q6: Which of the following is/are sources of
Q7: What is the difference between planned value
Q8: Which of the following offers the best
Q9: A project task is scheduled to begin
Q11: Which of the following project monitoring tools
Q12: Given the following information about a project
Q13: Consider the following project circumstances. Assume the
Q14: Which of the following is important to
Q15: What are possible values for earned value
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents