Which of the following is (are) true about time fences in a master production schedule system?
I. Changes far out in the planning horizon can be made with little or no cost to manufacturing.
II. In the "frozen zone," capacity and materials are committed to specific orders.
III. Changes in the near future on the planning horizon are less costly to make than changes far out.
A) I and II only
B) II and III only
C) I and III only
D) I, II, and III
E) none of the above
Correct Answer:
Verified
Q15: Which of the following is NOT an
Q16: If there are customer orders the projected
Q17: Which of the following are objectives of
Q18: The MPS:
A) facilitates order promising
B) works with
Q19: The functions of a master production schedule
Q21: Master scheduling is a balancing act between
Q22: A customer requests a new order in
Q23: Shifting customer design decisions as far down
Q24: Which of the following modules follows the
Q25: Which of the following is a contract
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents