A customer requests a new order in a period where there is inadequate material available in the available-to-promise (ATP) for that period, and the period is within the planning time fence. Which of the following is the best first course of action to take in such a situation?
A) Increase the master schedule quantity for that period by enough to cover the order
B) Shift the planning time fence inward
C) Tell the customer they cannot have the order in that period
D) Look for additional material in an earlier ATP quantity
Correct Answer:
Verified
Q15: Which of the following is NOT an
Q16: If there are customer orders the projected
Q17: Which of the following are objectives of
Q18: The MPS:
A) facilitates order promising
B) works with
Q19: The functions of a master production schedule
Q20: Which of the following is (are) true
Q21: Master scheduling is a balancing act between
Q23: Shifting customer design decisions as far down
Q24: Which of the following modules follows the
Q25: Which of the following is a contract
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents