Which of the following represents a major difference between a scheduled receipt and a firm planned order?
A) The computer can move the scheduled receipt, not the firm planned order
B) Only the scheduled receipt can occur within the planning horizon
C) Only the scheduled receipt represents a financial commitment
D) The scheduled receipt is generated from the master schedule, the firm planned order generated from MRP
Correct Answer:
Verified
Q16: The document that shows the component parts
Q31: Given the following parents and components,
Q32: Use the following MRP record and
Q33: The following two questions use the
Q34: Which of the following statements is best
Q35: Which of the following statements is best?
A)
Q36: Which of the following statements is best?
A)
Q37: Use the following MRP record and
Q38: Which of the following is elapsed time
Q40: In the following product trees the low
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents