One hundred units of part A are to be processed on a work center. The setup time is 2 hours and the run time per piece is 10 minutes. The total standard time will be:
A) 2 hours 10 minutes
B) 3 hours 40 minutes
C) 10 minutes
D) 1000 minutes
E) 1120 minutes
Correct Answer:
Verified
Q5: The available capacity will be influenced by:
Q6: is responsible for determining the capacity required
Q7: The capacity available with no regard for
Q8: A report that shows the future capacity
Q9: Over the previous three weeks a work
Q11: The percentage of time the work center
Q12: A work center was available for work
Q13: Information on the standard times for an
Q14: Rated capacity is calculated taking into account
Q15: Which of the following is NOT an