The normal capacity of the Malloy Company is 20,000 direct labor hours and 10,000 units per month.A finished unit requires 15 pounds of materials at an estimated cost of $1.00 per pound.The estimated cost of labor is $12.00 per hour.It is estimated that overhead for a month will be $15,000.
During the month of June,19,000 direct labor hours were worked at an average rate of $11.50 an hour.The number of units produced was 9,000,using all 132,000 pounds of material that were purchased at a cost of $1.05 per pound.
a.Prepare a standard cost summary showing the standard unit cost.
b.Calculate the material and labor variances.
c.Prepare entries in general journal form to charge materials and labor to work in process.Indicate whether the variances are favorable or unfavorable.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q60: Underapplied factory overhead would result if:
A)Factory overhead
Q61: In a three-variance method of factory overhead
Q62: Which of the following correctly demonstrates the
Q63: Perez Company adopted a standard cost system
Q64: The following information pertains to the Braun
Q66: In a four-variance method analyzing factory overhead,the
Q67: The following information is available from the
Q68: In a four-variance method analyzing factory overhead,the
Q69: In a three-variance method of factory overhead
Q70: The following information is available from the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents