The main difference between CPM and PERT is
A) the use of different activity time estimates.
B) PERT analysis is less expensive to conduct.
C) PERT lends itself to computerization while CPM networks must be constructed manually.
D) CPM integrates time and cost performance while PERT is based solely on time performance.
Correct Answer:
Verified
Q49: A project network is shown below. Use
Q50: For the project represented below, determine the
Q51: A project network is shown below. Use
Q52: A project consists of five activities. Naturally
Q53: Marcy Fetter, a staff analyst at the
Q54: Use the following network of related activities
Q55: Consider a project that has been modeled
Q56: Given the following network with activities and
Q57: Consider the following PERT/CPM network with estimated
Q58: A senior MIS design class project team
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents