A $38,000 Coil Winding and Unwinding Machine Is Estimated to Provide

Question 15

Essay

A $38,000 coil winding and unwinding machine is estimated to provide additional value to production by $15 per unit. When the machine is operated at 58 units per hour, it needs to be cooled down after 4 hours of operation and receive minor maintenance for 15 minutes. When the machine is operated at 118 units per hour, it needs to be cooled down after 5 hours of operation and receive minor maintenance for 30 minutes. The production line runs 8 hours per day. If each maintenance check costs $625 and the machine has a useful life of 80,000 hours of operations, at what speed should the machine should be operated?

Correct Answer:

verifed

Verified

At 58 units per hour, net increase in va...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents