Solved

Five Jobs Are Ready for Processing at Time Zero Through

Question 17

Multiple Choice

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
 Job  Processing Time (days)   Due Date A812B49C36D77E520\begin{array} { | l | l | l | } \hline \text { Job } & \text { Processing Time (days) } & \text { Due Date } \\\hline \mathrm { A } & 8 & 12 \\\hline \mathrm { B } & 4 & 9 \\\hline \mathrm { C } & 3 & 6 \\\hline \mathrm { D } & 7 & 7 \\\hline \mathrm { E } & 5 & 20 \\\hline\end{array}
Using the shortest processing time (SPT) rule, it can be concluded that the average flow time for these five jobs is _____.


A) more than 8 but less than or equal to 10 days.
B) more than 10 but less than or equal to 12 days.
C) more than 12 but less than or equal to 14 days.
D) more than 14 but less than or equal to 16 days.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents