Five Jobs Are Ready for Processing at Time Zero Through

Question 22

Multiple Choice

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
 Job  Processing Time (days)   Due Date  A 511 B 616 C 319 D 410 E 29\begin{array} { | l | l | l | } \hline \text { Job } & \text { Processing Time (days) } & \text { Due Date } \\\hline \text { A } & 5 & 11 \\\hline \text { B } & 6 & 16 \\\hline \text { C } & 3 & 19 \\\hline \text { D } & 4 & 10 \\\hline \text { E } & 2 & 9 \\\hline\end{array}
Using the earliest due date (EDD) rule, the average lateness for the five jobs is:


A) more than -6 but less than or equal to -2 days.
B) more than -2 but less than or equal to 2 days.
C) more than 2 but less than or equal to 6 days.
D) more than 4 but less than or equal to 8 days.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents