Question 21
Multiple Choice
Which of the following was NOT stated as contributing to the complication of estimating amount of interest carry?
Question 22
Multiple Choice
The amount to be paid to the lender from each lot sale is included in the:
Question 23
Multiple Choice
Generally, which of the following is FALSE regarding interest rate risk management techniques?
Question 24
Multiple Choice
Each parcel of land in a new development is selling for $15,000 and the total project revenue is estimated to be $5,000,000. The project lender has stated that the loan should be paid off when 80% of the total project revenue has been earned. The total loan amount is $3,500,000. What is the release price for each parcel?
Question 25
Multiple Choice
When financing land development, the lender generally requires the developer to submit which of the following?
Question 26
Multiple Choice
A futures instrument, such as a T-bill, can be used to hedge a cash or a spot instrument such as the prime rate, where the two instruments are not perfectly correlated. What type of hedge is this referred to as?