Suppose that you work at a local convenience store. The store has just closed and you and one other co-worker must complete a list of tasks before any of you can leave for the night. Each task may only be worked on by one person. What is the optimal amount of time that it will take to complete the list of tasks knowing that all tasks are independent from one another? 
A) 28
B) 35
C) 37
D) 42
E) None of the above.
Correct Answer:
Verified
Q22: Which of the digraphs below have an
Q23: A project consists of seven tasks labeled
Q24: Consider the project digraph shown below; what
Q25: Consider the project digraph shown below; what