This Is a Three-Part Question About Critical Path Calculation \bullet Given the Data Path Latencies Above, Which Instruction Determines the a Simple

Question 19

Essay

This is a three-part question about critical path calculation. Consider a simple single- cycle implementation of MIPS ISA. The operation times for the major functional components for this machine are as follows:
- This is a three-part question about critical path calculation. Consider a simple single- cycle implementation of MIPS ISA. The operation times for the major functional components for this machine are as follows: -  Below is a copy of the MIPS single-cycle datapath design. In this implementation the clock cycle is determined by the longest possible path in the machine. The critical paths for the different instruction types that need to be considered are: R-format, Load-word, and store-word. All instructions have the same instruction fetch and decode steps. The basic register transfer of the instructions are: Fetch/Decode: Instruction <- IMEM[PC]; R-type: R[rd] <- R[rs] op R[rt]; PC <- PC + 4; load: R[rt] <- DMEM[ R[rs] + signext(offset)]; PC <- PC +4; store: DMEM[ R[rs] + signext(offset)] <- R[Rt]; PC <- PC +4;    (Part C) Use the total latency column to derive the following critical path information:  \bullet Given the data path latencies above, which instruction determines the overall machine critical path (latency)?  \bullet What will be the resultant clock cycle time of the machine based on the critical path instruction?  \bullet What frequency will the machine run? Below is a copy of the MIPS single-cycle datapath design. In this implementation the clock cycle is determined by the longest possible path in the machine. The critical paths for the different instruction types that need to be considered are: R-format, Load-word, and store-word. All instructions have the same instruction fetch and decode steps. The basic register transfer of the instructions are:
Fetch/Decode: Instruction <- IMEM[PC];
R-type: R[rd] <- R[rs] op R[rt]; PC <- PC + 4;
load: R[rt] <- DMEM[ R[rs] + signext(offset)]; PC <- PC +4; store: DMEM[ R[rs] + signext(offset)] <- R[Rt]; PC <- PC +4;
 This is a three-part question about critical path calculation. Consider a simple single- cycle implementation of MIPS ISA. The operation times for the major functional components for this machine are as follows: -  Below is a copy of the MIPS single-cycle datapath design. In this implementation the clock cycle is determined by the longest possible path in the machine. The critical paths for the different instruction types that need to be considered are: R-format, Load-word, and store-word. All instructions have the same instruction fetch and decode steps. The basic register transfer of the instructions are: Fetch/Decode: Instruction <- IMEM[PC]; R-type: R[rd] <- R[rs] op R[rt]; PC <- PC + 4; load: R[rt] <- DMEM[ R[rs] + signext(offset)]; PC <- PC +4; store: DMEM[ R[rs] + signext(offset)] <- R[Rt]; PC <- PC +4;    (Part C) Use the total latency column to derive the following critical path information:  \bullet Given the data path latencies above, which instruction determines the overall machine critical path (latency)?  \bullet What will be the resultant clock cycle time of the machine based on the critical path instruction?  \bullet What frequency will the machine run? (Part C)
Use the total latency column to derive the following critical path information:
\bullet Given the data path latencies above, which instruction determines the overall machine critical path (latency)?
\bullet What will be the resultant clock cycle time of the machine based on the critical path instruction?
\bullet What frequency will the machine run?

Correct Answer:

verifed

Verified

The store instruction determines the ove...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents